PRIMARY SAG MILL

Scanning of the SAG Mill was completed in 2 hours, scans registration was completed on site to ensure all required data was collected. 3D Models of the AG Mill and the wear liners were created from the scan data, the assembly model was then compared to the scan data for analysis. A wear report was completed from the collected and processed data.


OBJECTIVE
  • Design rotable lower cone section to be flange fitted to existing Cone.
  • Fabricate & Rubber Line in Batam and ship to Australia.
  • Supply MDR & Detail design drawings for change management.
  
TIME FRAME
  • Scans completed in 2 hours, Post processing completed in 12 hours.
  • 3D Models and Detail Drawings completed in 40 hours. 

DELIVERABLES
  • Fully fabricated cone section, delivered on time for shutdown.
  • Full MDR & detail design / manufacturing drawings.

BENEFITS

As this was a retro fit design to an existing OEM asset no drawings existed, the use of 3D laser scanning allowed us to obtain all necessary data to design a new cone section to fit exactly as desired.